  • Phase 1 – April 4th – June 30th – From Neel Street to W7th/W8th Intersection = Single Lane Closure
  • Phase 2 – July 1st – July 31st – W8th/SR-837 Intersection to SR-837 Overhead RR Bridge = Complete Closure with Detours (Forest Ave. to West Run to Interboro to Mifflin Rd.)
  • Phase 3 – Aug. 1st – Sept. 20th – W7th/W8th Intersection to W8th/SR-837 Intersection = Complete Closure with Detours (W8th Ave to W8th/SR-837 Intersection)

Project official end date = Nov 4th.  There may be single lane closures from Sept. 20th thru Nov 4th

2022 SR-837 Project Map